Heřmanův Městec
Date of project/implementation: 2006/2006-2007
Four tanks with a nominal volume of 10,000 m3.
The project was to design the deep foundation of the constriction of fuel tanks, fire tank design and design of retaining structures, which were designed by the system of embankments reinforced with geosynthetics gabion face. The tanks are founded on a reinforced concrete slab which lays on the improved soil with gravel pillar (technology FRANKI).